Correlated courses in woodwork and mechanical drawing
Ira Samuel Griffith

THE CLASSIC COLLECTION · 1916
"Carpentry" by Ira Samuel Griffith is a practical guide on the fundamentals of carpentry written in the early 20th century. The text serves as an elementary treatise intended for apprentices, vocational and trade school students, highlighting essential techniques and principles of carpentry, with a focus on roof framing and structural integrity. At the start of "Carpentry," the author introduces the importance of foundational work in carpentry, emphasizing the role of carpenters in laying out foundations alongside masons. Griffith discusses the tools required for accurate measurements, such as the builder's transit and the Y-level, detailing how to properly establish a building site's grade line. He outlines the processes for excavating foundations, constructing footings, and selecting appropriate materials, providing a thorough overview of foundational principles essential for successful carpentry projects.
Introduction adapted from the source catalogue; source summaries may be automatically generated.
Free to read · English · 37,365 words · No account needed
MAKE TIME FOR A GOOD BOOK
On by default. Untick to stop anonymous reading totals. Each page counts after 10 seconds in view. How this works.
Anonymous counting is on unless you have switched it off.
To determine the number of bricks in a wall, multiply each square foot of surface by 7 (sometimes 7½ is used) which is the average number of bricks per foot of wall when 4" thick. Add 5% for breakage. Deduct for openings over 2' square. For walls thicker than 4", make suitable allowance.
A mason can lay 800 to 1000 common and 300 to 400 face bricks in a day.
Bricks may be laid in lime mortar or in cement mortar.
Brick, 1000 @ ............................
Lime, 3 bu. @ ............................
Sand, ½ cu. yd. @ ........................
Mason, 10 hrs. @ .........................
Tender, 10 hrs. @ ........................
-------
Total $
Brick, 1000 @ ............................
Portland cement, 1¼ bbl. @................
Sand ½ cu. yd. @ .........................
Mason, 10 hrs. @ .........................
Tender, 10 hrs. @ ........................
-------
Total $
=Chimneys.=--One foot of chimney height will contain five courses
of ordinary bricks.
No. Size of Size of No. Bricks
Flues Flue Chimney per Ft.
1 8" × 8" 16" × 16" 30
2 8" × 8" 16" × 28" 50
3 8" × 8" 16" × 40" 70
1 12" × 12" 20" × 20" 40
=Slate Roof.=--Exposure of each slate will equal the length of a slate diminished by 3" (the usual amount of lap) divided by 2, multiplied by the width of the slate.
To determine the number of slates required, divide the area to be covered by the exposure of each slate as determined just above.
Example--Determine the number of 6" × 12" slates required to
cover a surface 16' × 20'.
Solution--( (12" - 3") / 2) × 6" = 27 sq. in. (16 × 20 × 144") / 27" = 1707 slates.
Size Length of Expos. No. Req. Nails Req.
6" × 12" 4½" 533 3.8 lbs.
7" × 14" 5½" 377 2.66
8" × 16" 6½" 277 2
9" × 18" 7½" 214 1.5
Slate, @ .............................
Slater, 8 hrs., @ ....................
Roofing Paper, @ .....................
Placing paper, 20 min ................
Nails, 2 lbs. (8" × 16" slate) @ .....
--------
Total $
Metal work extra.
=Plastering.=--Plastering is estimated by the square yard. In estimating the number of square yards, deduct ½ the area of openings. The extra labor involved in working around grounds is thus allowed for. Strips of plastering less than 1 foot wide are estimated as a foot in width. Closet areas are increased by J/ to make allowance for the extra labor involved in working small surfaces. Special plastering of cornice, etc., will be charged extra: Lathing is usually a part of the plasterer's contract, tho done by a different set of workmen. The unit is either the square yard or the 1000 laths.
Lath, 1500 @ .........................
Nails, 10 lbs. 3d fine @ .............
Lather, 8 hrs. @ .....................
--------
Total ............................$
Lime, 10 bu. @ .......................
Hair, 6 lbs. @ .......................
Sand, 1 yd. @ ........................
2 plasterers, 12 hrs. each @ .........
1 helper, 12 hrs. @ ..................
--------
Total ............................$
Lime, 13 bu. @ .......................
Hair, 8 lbs. @ .......................
Sand, 1½ yds. @ ......................
Plaster of Paris, 1 bbl. @ ...........
2 plasterers, 16 hrs. each @ .........
1 helper, 16 hrs .....................
-------
Total ............................$
=Painting.=--Painting is estimated by the square yard, no deductions being made for openings such as doors and windows. Railings, grills, etc., are figured as if solid.
Your reading position is saved on this browser. Take it to another device with a library code. Reading pages adapt to text, rather than matching a printed edition.
BEHIND THE BOOK
This eBook is for the use of anyone anywhere in the United States and most other parts of the world at no cost and with almost no restrictions whatsoever. You may copy it, give it away or re-use it under the terms of the Project Gutenberg License included with this eBook or online at www.gutenberg.org. If you are not located in the United States, you will have to check the laws of the country where you are located before using this eBook. Read the source licence.
The original source file, including credits and licence, is retained by this library. Request an original-format copy at no charge. Please include the book title and Project Gutenberg identifier #70226.
KEEP YOUR CURIOSITY GOING

Charles G. (Charles Griffith) Ross
Hannah Webster Foster

Emily Lawless
Edwin Hamlin Carr

Charles De Lano Hine
Andrew Ure